The working principle of the powder material transport vehicle is to use the power of the vehicle to drive the air compressor, and send the compressed air into the air chamber at the lower part of the sealed tank through the pipeline, so that the powder and particles on the fluidized bed of the air chamber are suspended into a fluid state. When the pressure in the tank reaches the rated value, the discharge valve is opened, and the fluidized material flows through the pipeline for transportation. This time, let's take a look at the loading and unloading requirements and points of attention for the powder and granular material transport truck.

What should be paid attention to when loading the semi-trailer for the first powder and granular material transportation

1. Before opening the manhole, be sure to open the pressure relief valve to check whether the pressure in the tank is the same as the atmospheric pressure, that is, the value of the pressure gauge is zero.

2. After opening the manhole, check whether there is agglomerated powder or granule in the tank, especially the tank that has been filled with powder or granule and has not been used for a long time. Check carefully to remove the agglomerated powder or granule.

3. Put the materials into the tank.

4. After the filling is completed, because the sealing ring of the feed port has accumulated powder, it should be cleaned before closing the feed port to ensure the sealing performance.

What to pay attention to when unloading the second ash semi-trailer

1. Connect the discharge pipe to the place where it needs to be connected to ensure a reliable seal.

2. Close the discharge valve, pressure relief valve, external air valve and secondary air valve.

3. Start the engine, when the brake pressure reaches 392kPa, step on the clutch pedal, pull out the handle of the pneumatic switch valve of the power take-off box in the cab, put the power take-off box in gear, and then slowly release the pedal to make the air compressor run Only when it is stable, can the hand throttle be increased to make the speed reach the rated speed and inflate the air chamber in the tank.

4. When the pressure in the tank, that is, the pressure gauge reads 196kPa, open the discharge butterfly valve. During the conveying process, if the pressure rises to exceed 196kPa, the pipeline is blocked.

5. Control the hand throttle to keep the ash unloading pressure at 145-165kPa, and the general unloading speed is 1.2T/min. When the ash unloading is completed, the pressure in the tank drops to 9.8-19.6kpa. At this time, the secondary air ball valve should be opened to make All ash unloading pipelines are dredged.

6. Release the accelerator pedal, step on the clutch pedal, disconnect the power take-off, and stop the air compressor.

7. Open the pressure relief valve to discharge the remaining compressed gas in the tank so that the pressure in the tank is equal to atmospheric pressure, and it can avoid the "clamshell" accident when the feed port is opened.

8. When the horizontal distance is 5 meters and the input height exceeds 15 meters, after opening the butterfly valve to discharge the material, then the secondary air ball valve should be opened to dilute the powder and granular concentration and increase the ash discharge height.

Finally, the points of attention of the powder material transport vehicle

1. When charging and building pressure, when the pressure in the tank is too high and the safety valve is opened, the exhaust valve can be opened to reduce pressure;

2. When water enters the tank, the water should be discharged in time through the two drain valves at the bottom of the tank. If the fluidized bed canvas gets wet, the fluidized bed canvas should be replaced in time to avoid cement agglomeration on it

3. During the unloading process, if other abnormal conditions need to terminate the unloading, the unloading disc valve can be closed first, and then the pressure in the fluidized chamber can be unloaded by opening the exhaust valve.


Share:
  • wechat
Chat with Us

Contact Us
  • E-mail: lhautoparts88@gmail.com
  • Tel.: +86 17686798823
  • Fax: +86 531 6865 8175
  • Skype: lhaxle@outlook.com
  • WhatsApp: +8617686798823
  • Add.: Room 1110, Building 2, Hisense Xianwen Center, Industrial South Road, High-tech Zone, Jinan City, Shandong Province
Request a Quote